Bogner Construction Company is currently working on the following projects:
The college of wooster scot center; Wooster, OH
The Scot Center is a $30 million Student Recreation Center. This project started on May 11th, 2010 and is on schedule to obtain a Certificate of Occupancy on December 16th.

A project "snap shot" of several material quantities:
- Moved 35,000 cubic yards of earth/rock
- Installed 8,500 linear feet of water/storm sewer/sanitary sewer lines
- Poured 6,364 cubic yards of concrete incorporating 374 tons of reinforcing bars
- Set 30,000 sq. ft. of precast concrete planks
- Set 524 tons of structural steel
- Electrical:
- 17.8 miles of conduit
- 95.9 miles of electrical/IT wiring
- 1,350 light fixtures
- Mechanical:
- 7.38 miles of plumbing and sprinkler pipe
- Controlled by 455 valves
- 40.52 tons of sheet metal
- 7.38 miles of plumbing and sprinkler pipe
- Finishes:
- 110,000 linear feet of metal studs
- 104,000 sq. ft. of drywall
- 12,000 pieces of ceramic tile
- Including a Fighting Scot Logo
- 575 gallons of Pittsburgh Paint
- Applied with 100% Wooster Brush Co. tools
- Masonry:
- 275,000 face bricks
- 47,614 paving bricks
- 77,500 8" concrete block
- 260 cubic yards of structural block grout fill
- 1,200 pieces of decorative stone trim
- All of which required the mixing of 2,950 batches of mortar.
- 17,445 sq. ft. of ultra high efficiency glass
- Total man hours expended through December 7th ... 212,940
- Lost Time Accidents ... ZERO
- Original Milestone Schedule (in April 2010) Completion Date ... December 16, 2011
- Scot Center will finish on schedule!

![]()
Amster frick building; wooster, OH
Bogner Construction is currently working on the Amster Frick Building. This project consists of a replacing the mansard roof and masonry repairs to a downtown Wooster building.

![]()
Dix communications; KENT, OH
Bogner Construction Company is currently working on additions and renovations to a building for Dix Communications.

![]()
PNc bank projects; Throughout ohio
Bogner Construction Company has been working with PNC Bank completing miscellaneous projects throughout their different branches in Ohio. We will be starting to work on interior/teller line renovations and security improvements to a couple of Zainesville branches and a Belden Village branch. Over the last year we have completed the following jobs:
- Green: Total replacement of the parking lot, including new sanitary sewer line and water line installation
- Jackson Belden: Separation wall and doors & Teller Line Replacement
- Mayfield-Warrensville: Teller Line Replacement
- Medina River Styx: Interior Renovation
- Rittman: Interior Renovation
- Massillon: Lake Avenue Interior Renovation
- Zanesville: Teller Line Replacements at 2 Branch Locations
- Cambridge: Teller Line Replacement
- Minerva: Teller Line Replacement


![]()
Miscellaneous projects
Bogner Construction Company is completing projects for the following in addition to those above:
Holmes Cheese (Digester Tank & Slicing Room)
Akron Brass (New Bypass Line & Concrete Test Deck)
Wayne College (Replace Light Pole Base)
United Methodist Church (Misc. Work at Parsonage)
Wooster Brush (Silos)
upcoming 2012 projects
Bogner Construction Company will be working on the following upcoming projects in addition to those above (Check back for updates):
Rittman Waste Water Treatment Plant (January)
PNC Bank - Main Davidson (January 23-February 22)
PNC Bank - Reynoldsburg (January 30-February 17)
PNC Bank - Morse/Hamilton (March 5-March 26)
PNC Bank - Olentangy (March 5-March 26)
Hospice & Palliative Care of Greater Wayne County - New 12 Bed Inpatient Facility (March)
Buckeye Veal Waste Water Treatment Plant (Spring)
Wayne County Historical Society - Foundation for Carriage House & Parking Lot (Spring)
Selby Insectory Laboratory Renovation (Spring)
Hillcrest Waste Water Treatment Plant (Spring)
OARDC Site & Parking Lot (Spring)